  • The project involved the complete renovation of an existing 85,000 SF building for the relocation /expansion of manufacturing facilities relocating from NJ and MA.
  • The project broke down into 17,000 SF of ISO 7/8 cleanrooms for Teleflex manufacturing, packaging and labeling for production as well as a warehouse, R&D Lab, QC Labs, assembly, a new boiler room and 20,000 SF of office.
  • Construction required a focus on procurement of all MEP’s prior to completion of final design in order to meet the very aggressive project schedule.