Project Highlights:

  • IMDx required a new Corporate Headquarters with lab and manufacturing areas to meet their expanding business needs. To satisfy IMDx’s rapid growth, the project team provided early release packages for MEP’s, building steel and laboratory casework.
  • The project was executed over an 18 week period with second shift work as required to meet the aggressive schedule.
  • Major elements of the project included: 15,000 SF of BSL-2 Lab & Manufacturing space; 13,000 SF of office area, warehouse & freezer farm; new electrical and gas services; new standby generator; pH neutralization system; new boiler room and bathroom cores and new roof dunnage to support major mechanicals.