Project Highlights:

  • The project consisted of the redesign of the lobby to renovate and/or replace most every surface material and carpet, that included work turnstiles, new seating areas and security desk alterations. The project also included a new fitness center with showers, and the relocation and expansion of the kitchen.
  • As much work as possible was completed during the day in the occupied building. The noisy/dusty/vibration/vapor work was completed off-hours (nights and weekends) which included trenching, coring, hammer drilling, track shooting, etc.
Quincy, MA
New York, NY
617.801.0200
info@jcalnan.com